The Challenge
This project speaks for itself. When Marks & Spencer needed 700 bays of 11-metre tall adjustable pallet racking removed from their Daventry facility, they needed a team they could trust to deliver quickly, safely, and with minimal disruption.
With over 6,000 beams and 1,500 floor studs to contend with, this was an enormous undertaking by any measure — and one that demanded precision, experience, and a highly organised crew.
The Solution
We completed the full removal and transported everything off site in just 9 days — a remarkable achievement for a project of this scale. Every beam was stripped, every floor stud was cut, and the entire site was cleared within the agreed timeframe.
We're proud to say that Marks & Spencer were so impressed with our work that we are now contracted to carry out further racking removal projects for them in the near future.
We also captured a time-lapse video of this project, which perfectly showcases how safe, efficient, and well-organised our pallet racking removals are — even at the largest scale.
Project Highlights
- 700 bays of 11m tall adjustable pallet racking removed
- 6,000+ beams stripped and transported off site
- 1,500 floor studs cut
- Full clearance completed in just 9 days
- Ongoing relationship with Marks & Spencer for future projects